Question: Question1: Ackerman's Garage uses standards to plan and control labor time and expenses. The standard time for for an engine tune-up is 3.5hours, and the

Question1: Ackerman's Garage uses standards to plan and control labor time and expenses. The standard time for for an engine tune-up is 3.5hours, and the standard labor is $ 17 per hour. Last week, 26 tune-ups were completed. The labor efficiency variance was 13 hours unfavorable and the labor rate variance totaled $ 82 favorable.

a) Calculate the actual direct labor hourly rate paid for tune-up work last week. Round your answer to 2 decimal places.

b)Calculate the dollar amount of the labor efficiency variance.