Question: Acquisition Cost: $5MM Project Development Cost: $22.2MM Project Duration: 44 Months Bank @ 100% of Acquisition (I/Y = 8.25%) Bank @ 30% of Development Costs
- Acquisition Cost: $5MM
- Project Development Cost: $22.2MM
- Project Duration: 44 Months
- Bank @ 100% of Acquisition (I/Y = 8.25%)
- Bank @ 30% of Development Costs for 90% of the project duration
- Mezz @ 40% of Development Costs (I/Y = 14.25%) for 60% of the project duration
- Preferred Equity @ 20% of Development Costs (I/Y = 19.25%) for 40% of the project duration
- Common Equity @ The rest of Development Costs (I/Y = 23.0%) for 15% of the project duration
- Exit Strategy: Build and Hold. Refinance terms: 100% of Total Project Cost @9.25% for 25 years.
Find:
Amount borrowed from each lender/partner.
Capitalized Interest for each loan/investment
Total Project Cost (including Capitalized Interest)
Monthly Debt Service after completion/Refinance
Bonus Points: Find Effective Interest, NOI assuming 6% Cap Rate.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock