Question: Act Predecessor Optimistic Most likely Pessimistic a - 3 6 8 b - 2 4 4 c - 1 2 3 d a,b 6 7
| Act | Predecessor | Optimistic | Most likely | Pessimistic |
|
| a | - | 3 | 6 | 8 |
|
| b | - | 2 | 4 | 4 |
|
| c | - | 1 | 2 | 3 |
|
| d | a,b | 6 | 7 | 8 |
|
| e | c | 2 | 4 | 6 |
|
| f | e | 6 | 10 | 14 |
|
| g | e | 1 | 2 | 4 |
|
| h | d | 3 | 6 | 9 |
|
| i | g,h | 10 | 11 | 12 |
|
| j | f,g | 14 | 16 | 20 |
|
|
|
|
|
|
|
|
4.1 Using PERT, calculate the time (t) for each activity. (10)
4.2 Draw the network diagram (AON) based on the above and identify the critical path. (15)