Question: Activities 1 , 2 , 3 , and 4 are described in the network diagram and happen concurrently. Activity 1 is 4 days, Activity 2

Activities 1,2,3, and 4 are described in the network diagram and happen concurrently. Activity 1 is 4 days, Activity 2 is 7 days, Activity 3 is 4 days, and Activity 4 is 5 days. Which statement is most accurate?
Activity 1 and 3 are on the critical path.
Activity 2 has zero float.
Activity 1 and 3 both have 4 days of float.
Activities 1,3, and 4 must be completed within 4 days.