Question: Activities A, B, and C are started at Week 0 and are the immediate predecessors for Activity J. If the earliest finish times for the

 Activities A, B, and C are started at Week 0 and

Activities A, B, and C are started at Week 0 and are the immediate predecessors for Activity J. If the earliest finish times for the three activities are Week 11, Week 15, and Week 10, respectively, then the earliest start time for J will be A. Week 10 B. Week 11 C. Week 12 D. Week 15