Question: Activities ( A through G ) and their expected times ( in days ) are given by the In order to reduce / crash the

Activities (A through G) and their expected times (in days) are given by the
In order to reduce/crash the completion time of this project by one feasibly crashed by one day, which of the following should you do?
Crash F by one day at a cost of $300.
Crash G by one day at a cost of $440.
Crash E by one day at a cost of $500.
Crash B by one day at a cost of $225.
Crash D by one day at a cost of $300.