Question: Activities and their time estimates for a project are given as follows. Fill in the blanks below. Time estimates Immediate Expected variance Activity Predecessor Optimistic

Activities and their time estimates for a project

Activities and their time estimates for a project are given as follows. Fill in the blanks below. Time estimates Immediate Expected variance Activity Predecessor Optimistic likely Most Pecsimisti Time (ET) 59509 60 77 44 65 40 16 4 |32 41 The estimated expected (mean) time for project completion is Select] The probability that this project will be completed after 120 days is Select]