Question: Activities can be delayed only to the point where all their positive slack is used up , as any further delays would cause the project
Activities can be delayed only to the point where all their positive slack is used up as any further delays would cause the project to
a extend beyond the project completion time.
b be completed ahead of schedule.
c increase costs of all the activities in the project.
d increase its requirements for additional resources for all activities.