Question: Activities following a node a . have an earliest start time equal to the largest of the earliest flnish times for all activities enteriog the
Activities following a node
a have an earliest start time equal to the largest of the earliest flnish times for all activities enteriog the node
b can begin as soon as any activity preceding the node has been completed.
c have a latest start time equal to the largest of the earliest finish times for all activities entering the node.