Question: Activities: Foundations: Incurred cost 2 4 0 0 , actual % complete 1 0 0 % Floor: Incurred cost 1 5 0 0 , actual
Activities:
Foundations: Incurred cost actual complete
Floor: Incurred cost actual complete
Building: Incurred cost actual complete
ElectricalPlumbing: Incurred cost actual complete
Finishing: Incurred cost actual complete
With the above tables calculate the:
Actual value AV ACWP
Earned value EV BCWP
Planned valuePV BCWS
Cost performance index CPI
Cost varianceCV
Scheduled performance indexSPI
Schedule variance
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Answer Earned Value Analysis for Project Based on the information provided we can calculate the following Earned Value metrics 1 Actual Cost AC This i... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
