Question: Activities: Foundations: Incurred cost 2 4 0 0 , actual % complete 1 0 0 % Floor: Incurred cost 1 5 0 0 , actual

Activities:
Foundations: Incurred cost 2400, actual % complete 100%
Floor: Incurred cost 1500, actual % complete 100%
Building: Incurred cost 2700, actual % complete 50%
Electrical/Plumbing: Incurred cost 700 actual % complete 25%
Finishing: Incurred cost 0 actual % complete 0
With the above tables calculate the:
1. Actual value - AV (ACWP)
2. Earned value - EV (BCWP)
3. Planned value-PV (BCWS )
4. Cost performance index - CPI
5. Cost variance-CV
6. Scheduled performance index-SPI
7. Schedule variance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer Earned Value Analysis for Project Based on the information provided we can calculate the following Earned Value metrics 1 Actual Cost AC This i... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!