Activities: Foundations: Incurred cost 2 4 0 0 , actual % complete 1 0 0 % Floor:
Fantastic news! We've Found the answer you've been seeking!
Question:
Activities:
Foundations: Incurred cost actual complete
Floor: Incurred cost actual complete
Building: Incurred cost actual complete
ElectricalPlumbing: Incurred cost actual complete
Finishing: Incurred cost actual complete
With the above tables calculate the:
Actual value AV ACWP
Earned value EV BCWP
Planned valuePV BCWS
Cost performance index CPI
Cost varianceCV
Scheduled performance indexSPI
Schedule variance
Related Book For
Income Tax Fundamentals 2013
ISBN: 9781285586618
31st Edition
Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill
Posted Date: