Question: Activities I, J, and K are the immediate predecessors for activity L. If the earliest finish times for the three are 14, 12, and 15,

Activities I, J, and K are the immediate

Activities I, J, and K are the immediate predecessors for activity L. If the earliest finish times for the three are 14, 12, and 15, then the earliest start time for L. is 12. is 14. cannot be determined. is 15