Question: Activities H , I, and K are the immediate predecessors for activity X . If the earliest finish times for the three are 1 2

Activities H, I, and K are the immediate predecessors for activity X. If the earliest finish times for the three are 12,16, and 14, then the earliest start time for X
Question 9 options:
is 12.
is 14.
is 16.
is 42.