Question: Activities on the critical path are critical because Select one: a. These activities evidence the largest variation in completion times. b. These activities represent the

Activities on the critical path are critical because

Select one:

a. These activities evidence the largest variation in completion times.

b. These activities represent the largest expenditure for labor and materials.

c. These activities are the most difficult to manage.

d. Delay of these activities will delay project completion time.

e. None of the above