Question: Activities on the critical path are critical because they represent the minimal project completion time any delay in critical activities will affect the project completion

Activities on the critical path are critical because
they represent the minimal project completion time
any delay in critical activities will affect the project completion time
they represent the most expensive activities in terms of resources
a&b
all of the above