Question: The activities on the critical path are ____ (example, B- F - H) The total project completion time for Dave = __ (weeks) Please include

The activities on the critical path are ____ (example, B- F - H)
The total project completion time for Dave = __ (weeks)
Please include the SLACK times
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: O Immediate Predecessor(s) Time Activity (weeks) 7 B 8 C 2 D 2 Time Activity (weeks) E 3 F 6 G 9 Immediate Predecessor(s) B B CE DF A H 7 Dave's earliest start (ES) and earliest finish (EF) are: ES EF Activity A 7Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
