Question: Activities: W , X , Y , Z Durations: W = 5 days, X = 7 days, Y = 3 days, Z = 4 days

Activities: W, X, Y, Z
Durations: W =5 days, X =7 days, Y =3 days, Z =4 days
Costs (Normal): W = $800, X = $1,300, Y = $600, Z = $1,100
Costs (Crashed): W = $1,000, X = $1,700, Y = $900, Z = $1,400
Precedence: X follows W, Y follows W, and Z follows both X and Y.
Lags: There is a Finish to Start (FS) lag of 3 days between W and X, and a Start to Start (SS) lag
of 2 days between W and Y.
Based on this information, answer the following questions:
Question 1: Calculate the Total Normal Cost of the Project. And calculate the total cost of the
project if no activities are crashed.
Question 2: Determine the Critical Path.
Identify the critical path of the project considering the activity durations and lags.
Question 3: Calculate the Total Cost of the Project if Activity X is Crashed. If crashing activity
X reduces its duration by 2 days with an associated cost increase, calculate the new total cost of
the project.
Question 4: Determine the Project Duration After Crashing Activity X. And find out the new
project duration after activity X is crashed.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!