Question: Activities: W , X , Y , Z Durations: W = 5 days, X = 7 days, Y = 3 days, Z = 4 days
Activities: W X Y Z
Durations: W days, X days, Y days, Z days
Costs Normal: W $ X $ Y $ Z $
Costs Crashed: W $ X $ Y $ Z $
Precedence: X follows W Y follows W and Z follows both X and Y
Lags: There is a Finish to Start FS lag of days between W and X and a Start to Start SS lag
of days between W and Y
Based on this information, answer the following questions:
Question : Calculate the Total Normal Cost of the Project. And calculate the total cost of the
project if no activities are crashed.
Question : Determine the Critical Path.
Identify the critical path of the project considering the activity durations and lags.
Question : Calculate the Total Cost of the Project if Activity X is Crashed. If crashing activity
X reduces its duration by days with an associated cost increase, calculate the new total cost of
the project.
Question : Determine the Project Duration After Crashing Activity X And find out the new
project duration after activity X is crashed.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
