Question: Activities which can take place at the same time are termed Multiple Choice C critical path. O burst activity. O parallel activity. O independent activity.

Activities which can take place at the same time are termed Multiple Choice C critical path. O burst activity. O parallel activity. O independent activity. O merge activity