Question: ActivitiesNormal time (days) Normal cost ($) Crash cost ($ Q2 ) Find optimum project cost with considering indirect cost = 30 $ per day by
ActivitiesNormal time (days) Normal cost ($) Crash cost ($ Q2 ) Find optimum project cost with considering indirect cost = 30 $ per day by crashing Crash time (days ) 6 1 - 2 8 100 200 4 150 2 350 1-3 2-42 50 1 2-5 10100 5 90 400 200 3-4 5 100 4-5 3 80100
QUESTIONS Activities Normal time (days) Normal cost ($) Crash cost ($) Crash time (days) 6 1-2 8 100 Q2) Find optimum project cost with considering indirect cost = 30 $ per day by crashing 200 350 1-3 4 150 2 2-4 2 50 1 90 10 5 400 2-5 3-4 100 100 5 1 200 100 3 4-5 80 1
Step by Step Solution
There are 3 Steps involved in it