Question: QUESTIONS Activities Normal time (daya) Normal cost ($) Crash Cost($) Q2) Find optimum project cost with considering indirect cost-30 per day by crashing Crash time

QUESTIONS Activities Normal time (daya) Normal

QUESTIONS Activities Normal time (daya) Normal cost ($) Crash Cost($) Q2) Find optimum project cost with considering indirect cost-30 per day by crashing Crash time (days) 6 2 1-2 8 1-3 200 350 1 2 10 100 150 50 100 100 80 2-5 3-4 4-5 5 1 5 90 100 200 100 3