Question: Activity 1 : How to setup work ( People and Equipment ) resources? There are two types of work resources in MS Project. One is
Activity : How to setup work People and Equipment resources?
There are two types of work resources in MS Project. One is people and the other one is
equipment.
People's resources might be flexible in tasks they can perform more than one job however,
equipment resources tend to be more specialized. So be careful in assigning both the resources
On the View menu, Click Resource Sheet
In the Resource Name field, enter the resources name
In the Type field, click Work
In the Max. Units field, type or click the maximum capacity of this resource to accomplish
any work in terms of
Enter any other useful information related to your project
Repeat step through for each resource.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock