Question: Activity 1 : How to setup work ( People and Equipment ) resources? There are two types of work resources in MS Project. One is

Activity 1: How to setup work (People and Equipment) resources?
There are two types of work resources in MS Project. One is people and the other one is
equipment.
People's resources might be flexible in tasks they can perform (more than one job), however,
equipment resources tend to be more specialized. So be careful in assigning both the resources
1. On the View menu, Click Resource Sheet
2. In the Resource Name field, enter the resources name
3. In the Type field, click Work
4. In the Max. Units field, type or click the maximum capacity of this resource to accomplish
any work in terms of %
5. Enter any other useful information related to your project
6. Repeat step 2 through 5 for each resource.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!