Question: Activity 7 is directly preceded by two activities activity 5 and activity 6 . Activity 5 has an expected duration of five and an ES

Activity 7 is directly preceded by two activitiesactivity 5 and activity 6. Activity 5 has an expected duration of five and an ES time of six. Activity 6 has an expected duration of seven and an ES time of seven. Activity 7 has an expected duration of 10. The ES for activity 7 is:
Select one:
a.
11
b.
14
c.
21
d.
24
e.
25