Question: Time left 0 : 5 5 : 4 2 Activity 7 is directly preceded by two activities - activity 5 and activity 6 . Activity

Time left 0:55:42
Activity 7 is directly preceded by two activities - activity 5 and activity 6. Activity 5 has an expected duration of five and an ES time of six. Activity 6 has an expected duration of seven and an ES time of seven. Activity 7 has an expected duration of 10. The ES for activity 7 is:
Select one:
a.11
b.14
c.21
d.24
e.25
An activity, A, has two succeeding activities, B and C. Given the following information,
 Time left 0:55:42 Activity 7 is directly preceded by two activities