Question: Activity A B C D E F G H 1 Predecessor s A A A B C D E E F G H Figure 7


Activity A B C D E F G H 1 Predecessor s A A A B C D E E F G H Figure 7 6 Network Scheduling Data Duration days 5 20 15 in 5 60 050 15 20 15 2 Consider the network scheduling data presented in Figure 7 6 How many days of slack are associated with activity E a 0 b 107