Question: Activity A B D E F G H A(3) Time (weeks) Reduce A by 3 4 D(6) 6 6 6 5 AON network diagram B(4)

Activity A B D E F G H A(3) Time (weeks) Reduce A

Activity A B D E F G H A(3) Time (weeks) Reduce A by 3 4 D(6) 6 6 6 5 AON network diagram B(4) 7 3 C(6) IF by week(s). Total additional cost is $ Normal Cost ($) 500 650 850 1,400 1,650 200 1.500 550 E(6) F(5) Crash Time (weeks) 2 3 week(s), D by 3 4 week(s), G by 4 5 5 3 G(7) week(s), B by (If there is no amount for a box enter O. All boxes must be filled.) Crash Cost ($) 910 750 1,360 2,060 2,150 200 1.800 550 H(3) Weeks Reduced 1 1 3 2 2 0 2 0 week(s), E by Crash Cost per Week ($) 410 100 week(s), H by 170 330 250 0 150 week(s), C by 0 week(s)