Question: Activity a m b Immediate Predecessor ( s ) Activity a m b Immediate Predecessor ( s ) A 4 8 1 2 - G

Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s)
A 4812- G 235 C, E
B 1824 A H 222 F
C 91218 A I 555 F
D 4610 A J 6712 D, G, H
E 134 B K 334 I, J
F 5920 C, E The estimated time for the critical path is