Question: Activity a m b Immediate Predecessor ( s ) Activity a m b Immediate Predecessor ( s ) A 8 1 0 1 1 -

Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s)
A 81011- C 9913 A
B 41017- D 6811 B
The expected completion time of the path other than the critical path=
18.34 weeks (round your response to two decimal places).
Part 8
c) The variance of the critical path=
enter your response here weeks (round your response to two decimal places).