Question: Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 2 6 9 - G 2 3 4 A, E B 10
| Activity | a | m | b | Immediate Predecessor(s) | Activity | a | m | b | Immediate Predecessor(s) |
| A | 2 | 6 | 9 | - | G | 2 | 3 | 4 | A, E |
| B | 10 | 11 | 12 | - | H | 3 | 5 | 7 | F |
| C | 1 | 2 | 3 | - | I | 11 | 12 | 13 | G |
| D | 7 | 8 | 9 | C | J | 13 | 15 | 17 | C |
| E | 3 | 5 | 7 | B, D | K | 5 | 9 | 13 | H, I |
| F | 6 | 9 | 13 | A, E |
b) Determine the total project completion time and the critical path for the project. Critical path activities are the activities that lie on the longest time path (in terms of time). The critical path follows the activities with slack = 0. Part 3 Activities on the critical path for the project are
c) Determine ES, EF, LS, LF, and slack for each activity.
d) What is the probability that Kelle Carpet and Trim will finish the project in 38 days or less?