Question: Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 4 9 12 - G 2 3 4 C, E B 2
Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 4 9 12 - G 2 3 4 C, E B 2 8 24 A H 2 2 2 F C 9 12 18 A I 7 7 7 F D 5 7 10 A J 4 7 14 D, G, H E 1 2 4 B K 3 3 4 I, J F 5 9 20 C, E
a) The expected (estimated) time for activity C is
weeks. (Round your response to two decimalplaces.)
b) The variance for activity C is
weeks. (Round your response to two decimalplaces.)
c) Based on the calculation of the estimated times, the critical path is
d) The estimated time for the critical path is
weeks. (Round your response to two decimalplaces.)
e) The activity variance along the critical path is
weeks. (Round your response to two decimalplaces.)
f) The probability that Hopkins Hospitality will finish the project in
40 weeks or less is
(Enter as a probability and round your response to three decimal places.)