Question: Activity (A) min. (8 months) most likely (9 months) max (13 months) predecessor (none) Activity (B) min. (5 months) most likely (6 months) max. (8
Activity (A) min. (8 months) most likely (9 months) max (13 months) predecessor (none)
Activity (B) min. (5 months) most likely (6 months) max. (8 months) predecessor (none)
Activity (C) min. (2 months) most likely (4 months) max. (7 months) predecessor (B)
- Calculate the expected value for activities A, B, and C
- Calculate the variance for the project
- What is the percent probability that the project will be completed in 11 months?