Question: this is all the question Months Months saved Activity Immediate Normal predecessors Max Most likely Min cost and cost incurred A 2 3 4 B
this is all the question
Months Months saved Activity Immediate Normal predecessors Max Most likely Min cost and cost incurred A 2 3 4 B 2 8 4 10 Iltam D 3 10 A E 5 13 CD B, C 2,100 1,200 2,500 2,400 5,400 11,200 2,450 1,100 1,800 2, $1,100 1, $250 2, $300 3, $1,500 2, $100 1, $400 2, $600 3, $1,350 2, $800 F 5 7 9 G 4 6 14 D H 1 1 7 E, F E,G I 1 3 5 a. Determine the critical path of the project. How soon can Mos. Co get the project done? b. Months passed, the total spending from the start date is estimated at $17,450. Mr. Mos, the project manager assures that the project has been on schedule and on budget. How many months has the project been done? How is the completion progress of each activity? c. Describe the crashing process and the additional expense since the new target deadline is of 15 months. d. Describe the crashing process and the additional expense since the new target deadline is of 13 months e. The penalty for not completing on time is $330 per month. How many months should Mr. Mos crash the project? Assume that the only implicit and explicit cost of project delay is the fine, and Mr. Mos is kind of the expense sensitive. The information of the Mos.Co's new project is provided in the following table Months Immediate Normal Months saved Activity Max Most likely Min predecessors cost and cost incurred A 2 3 4 2,100 B 2 2 8 1.200 4 4 10 D 2 3 10 A 2,500 2,400 5,400 11,200 E 3 5 13 C D B, C 2, S1,100 1, S250 2, S300 3, $1,500 2, 5100 1, $400 2, 5600 3, S1,350 2, 8800 F 5 7 9 G 4 6 14 D H 1 1 7 E, F E, G 2,450 1,100 1,800 1 3 5 a. Determine the critical path of the project. How soon can Mos. Co get the project done? b. Months passed, the total spending from the start date is estimated at $17,450. Mr. Mos, the project manager assures that the project has been on schedule and on budget. How many months has the project been done? How is the completion progress of each activity? c. Describe the crashing process and the additional expense since the new target deadline is of 15 months. d. Describe the crashing process and the additional expense since the new target deadline is of 13 months. e. The penalty for not completing on time is $330 per month. How many months should Mr. Mos crash the project? Assume that the only implicit and explicit cost of project delay is the fine, and Mr. Mos is kind of the expense sensitive