Question: Activity (A) Pessimistic (5 weeks) most likely (4 weeks) Optimistic (3 weeks) predecessor (S) Activity (B) Pessimistic (2 weeks) most likely (2 weeks) Optimistic (2

Activity (A) Pessimistic (5 weeks) most likely (4 weeks) Optimistic (3 weeks) predecessor (S)

Activity (B) Pessimistic (2 weeks) most likely (2 weeks) Optimistic (2 weeks) predecessor (T)

Activity (D) Pessimistic (9 weeks) most likely (5 weeks) Optimistic (1 week) predecessor (A)

Activity (M) Pessimistic (7 weeks) most likely (5 weeks) Optimistic (3 weeks) predecessor (U)

Activity (O) Pessimistic (9 weeks) most likely (2 weeks) Optimistic (1 week) predecessor (B)

Activity (P) Pessimistic (12 weeks) most likely (10 weeks) Optimistic (8 weeks) predecessor (D,M,Y)

Activity (R) Pessimistic (10 weeks) most likely (6 weeks) Optimistic (5 weeks) predecessor (T)

Activity (S) Pessimistic (3 weeks) most likely (2 weeks) Optimistic (1 week) predecessor (T)

Activity (T) Pessimistic (4 weeks) most likely (4 weeks) Optimistic (4 weeks) predecessor (--)

Activity (U) Pessimistic (1 weeks) most likely (1 week) Optimistic (1 week) predecessor (R)

Activity (Y) Pessimistic (15 weeks) most likely (10 weeks) Optimistic (5 weeks) predecessor (O)

What is the critical path and expected completion date if you start this project on November 1st 2022?

What is the probability that you will finish this project 2 weeks earlier than your expected time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!