Question: Activity (A) Pessimistic (9 weeks) most likely (6 weeks) Optimistic (3 weeks) predecessor (none) Activity (B) Pessimistic (7 weeks) most likely (5 weeks) Optimistic (3

Activity (A) Pessimistic (9 weeks) most likely (6 weeks) Optimistic (3 weeks) predecessor (none)

Activity (B) Pessimistic (7 weeks) most likely (5 weeks) Optimistic (3 weeks) predecessor (A)

Activity (C) Pessimistic (12 weeks) most likely (7 weeks) Optimistic (4 weeks) predecessor (A)

Activity (D) Pessimistic (10 weeks) most likely (8 weeks) Optimistic (4 weeks) predecessor (B)

Activity (E) Pessimistic (16 weeks) most likely (10 weeks) Optimistic (5 weeks) predecessor (C)

Activity (F) Pessimistic (5 weeks) most likely (4 weeks) Optimistic (3 weeks) predecessor (D,E)

Activity (G) Pessimistic (8 weeks) most likely (6 weeks) Optimistic (3 weeks) predecessor (D,E)

Activity (H) Pessimistic (10 weeks) most likely (6 weeks) Optimistic (5 weeks) predecessor (F)

Activity (I) Pessimistic (11 weeks) most likely (8 weeks) Optimistic (5 weeks) predecessor (G)

Activity (J) Pessimistic (3 weeks) most likely (3 weeks) Optimistic (3 weeks) predecessor (H,I)

  1. construct a network diagram using AON notation.
  2. calculate the expected time for each of the project activities.
  3. calculate the variance for each of the project activities
  4. calculate the completion time for this project.
  5. Identify the activities included on the critical path of this project.
  6. Calculate the probability that the project will be completed in 38 weeks.
  7. Calculate the probability that the project will be completed in 42 weeks.
  8. Please draw a DSM for this project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!