Question: Activity Activity Legend Activity Predecessor Activity Duration (weeks) Locate new facilities 1 - 5 Interview Staff 2 - 2 Hire and Train Staff 3 2
| Activity | Activity Legend | Activity Predecessor | Activity Duration (weeks) |
| Locate new facilities | 1 | - | 5 |
| Interview Staff | 2 | - | 2 |
| Hire and Train Staff | 3 | 2 | 3 |
| Select & Order Furniture | 4 | 1 | 2 |
| Remodel & install phones | 5 | 1 | 3 |
| Furniture received & setup | 6 | 4 | 2 |
| Move in | 7 | 3,5,6 | 1 |
Draw:
a) Gantt Chart. b) AOA Diagram . c) AON Diagram.
| Activity | Activity Legend | Activity Predecessor | Activity Duration |
|
| Design house and obtain financing | 1 | - | 3 | |
| Lay foundation | 2 | 1 | 2 | |
| Order and receive material | 3 | 1 | 1 | |
| Build house | 4 | 2,3 | 3 | |
| Select Paint | 5 | 2,3 | 1 | |
| Select Carpet | 6 | 5 | 1 | |
| Finish work | 7 | 4,6 | 1 |
- Draw an AON Diagram.
- Find out the critical path.