Question: Activity Activity Predecessor Activity Duration (In weeks) Slack a - 3 b 1 2 c 2 1 d 2 1 e 3,4 1 f 5
| Activity | Activity Predecessor | Activity Duration (In weeks) | Slack |
| a | - | 3 |
|
| b | 1 | 2 |
|
| c | 2 | 1 |
|
| d | 2 | 1 |
|
| e | 3,4 | 1 |
|
| f | 5 | 2 |
|
| g | 6 | 1 |
|
- Draw an Activity on Node network diagram and show the earliest and latest activity start and finish time.
- Find out the possible paths and the critical path.