Question: Consider a project having the following seven activities: Immediate Activity Predecessors Time (weeks) A none 3 B A 5 C B 4 D B 5
Consider a project having the following seven activities:
Immediate
Activity Predecessors Time (weeks)
A none 3
B A 5
C B 4
D B 5
E C 12
F D 8
G E, F 3
(a) What is the critical time?
(b) What is the critical path?
(c) What is the slack for each activity?