Question: Activity Activity Time (days) Immediate Predecessor(s) A 4 - B 4 A C 3 A D 3 B E 1 B F 6 B, C
Activity Activity Time (days) Immediate Predecessor(s)
A 4 -
B 4 A
C 3 A
D 3 B
E 1 B
F 6 B, C
G 2 D, E
H 6 F
I 5 F
J 5 G, H, I
The critical path is A-B-F-H-J and the project duration is 25 days.
How much slack is in each of the activities G, H, and I:
| Activity | Activity Time (days) | On critical path? | Slack (days) |
| G | 2 | No | 7 |
| H | 6 | Yes | 0 |
| I | 5 | No | 1 |
- Use the same data above and create a Gantt chart.
- Name the activity in Row 1 as "Project" and indent all the other activities as sub-tasks under "Project."
- Insert columns for Total slack, ES, EF, LS, LF