Question: Activity Activity Time (days) Immediate Predecessor(s) A 4 - B 4 A C 3 A D 3 B E 1 B F 6 B, C

Activity Activity Time (days) Immediate Predecessor(s)

A 4 -

B 4 A

C 3 A

D 3 B

E 1 B

F 6 B, C

G 2 D, E

H 6 F

I 5 F

J 5 G, H, I

The critical path is A-B-F-H-J and the project duration is 25 days.

How much slack is in each of the activities G, H, and I:

Activity

Activity

Time (days)

On critical path?

Slack

(days)

G

2

No

7

H

6

Yes

0

I

5

No

1

  • Use the same data above and create a Gantt chart.
  • Name the activity in Row 1 as "Project" and indent all the other activities as sub-tasks under "Project."
  • Insert columns for Total slack, ES, EF, LS, LF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!