Question: 4. Given the following network project : Activity Estimated time (days) Immediate predecessor A 2 - B 3 - C 4 - D 2 A,

4. Given the following network project:
Activity Estimated time (days) Immediate predecessor
A 2 -
B 3 -
C 4 -
D 2 A, B
E 1 C, D
F 3 A
G 5 F
H 2 C
I 4 E, G, H
J 7 I
K 3 J
a. Develop a network diagram.
b. How long will it take to complete the project?
c. Which activities are on the critical path?
d. How much stack is in each activity?
e. What is the impact on the critical time if the time for Activity B is reduced by 2 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!