Question: ( Activity B: Crash cost = 5 0 times 1 = 5 0 Activity C: Crash cost = 2 0 0 times 2
Activity B: Crash costtimes
Activity C: Crash costtimes
Activity D: Crash costtimes
Activity E: Crash costtimes
Activity F: Crash costtimes
Activity G: Crash costtimes
Total Direct Cost
Total Direct Cost
The total direct cost at maximum crash time is $
What is the optimum crash point in weeks and dollars pts
The optimum crash point?