Question: Activity B Duration Activity A Activity D Duration W Durationz Activity C Duration Y In the above network. W is 11 duys, X is 26

Activity B Duration Activity A Activity D
Activity B Duration Activity A Activity D Duration W Durationz Activity C Duration Y In the above network. W is 11 duys, X is 26 days. Z is 17 days, and Yis 5 days in duration Activity A starts on Dayo. Determine the earliest (ordinal) date that the project can finish, assuming that all activities start as soon as possible Enter your answer as a pure number who units