Question: Activity B Durationx Activity A Activity D Duration w Duration 2 Activity Duration In the above network, Wis 16 days, Xis 22 days. Z is

Activity B Durationx Activity A Activity D
Activity B Durationx Activity A Activity D Duration w Duration 2 Activity Duration In the above network, Wis 16 days, Xis 22 days. Z is 22 days, and Yin 7 days in duration Activity Astarts on Day Determine the latest (ordinal) date that Activity B can start without delaying the project, assuming that all activities start as soon as possible Enter your wors pure number without units QUESTION 40 Activity B Duration Activity A Activity VD Duration w Duration 2 Activity Duration Y In the above network, Wis 15 days X is a days, Z is 18 days, and Yis 22 days in duration, Activity A starts on Day and all activities start as soon as possibile. Determine the slack in Activity B. Enter your answer as a pure number wihtout units. Do not leave it blank, enter numerico if there is no slack

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!