Question: Activity B is directly followed by two activities-activity C and activity D. Activity C has an expected time of eight and a LF is 26.

Activity B is directly followed by two
Activity B is directly followed by two activities-activity C and activity D. Activity C has an expected time of eight and a LF is 26. Activity D has an expected time of six and a LF is 23. Activity B has an expected time of five. Activity B is directly precded by activity A. what is the LS for activity B? O 17 O 10 13 18 O 12