Question: Activity 8 is directly preceded by two activities - activity 7 and activity 6 . Activity 5 has an expected time of five days and

Activity 8 is directly preceded by two activities-activity 7 and activity 6. Activity 5 has an expected time of five days and an estimated start (ES) time of day 6. Activity 6 has an expected time of seven days and an ES time of day 7. Activity 8 has an expected time of 10 days. The EF for activity 8 is?
a. Day 14
b. Day 26
c. Day 21
d. Day 24
e. Day 19
 Activity 8 is directly preceded by two activities-activity 7 and activity