Question: Activity 8 is directly preceded by two activities - activity 7 and activity 6 . Activity 5 has an expected time of five days and
Activity is directly preceded by two activitiesactivity and activity Activity has an expected time of five days and an estimated start ES time of day Activity has an expected time of seven days and an ES time of day Activity has an expected time of days. The EF for activity is
a Day
b Day
c Day
d Day
e Day