Question: activity B , normal cost is 1 7 5 0 , crash cost is 9 2 5 0 , normal time is 6 , crash
activity B normal cost is crash cost is normal time is crash time is
The table shows normal time, crash time, normal cost, crash cost of an activity in a project. According to this table what is the crash cost per day for this activity?
Step by Step Solution
There are 3 Steps involved in it