Question: Activity C D % 5 10 15 20 25 30 35 Plan Complete 850 350 1,200 100% 400 125 525 100% 1,275 650 1,925 100%

Activity C D % 5 10 15 20 25 30 35 Plan Complete

Activity C D % 5 10 15 20 25 30 35 Plan Complete 850 350 1,200 100% 400 125 525 100% 1,275 650 1,925 100% 2800 4,500 350 7,650 95% 680 400 1,080 75% 125 875 1,000 80% 300 1200 1,500 45% 850 750 1,400 3,450 5,180 1,175 2,075 14,880 900 650 1,350 3,875 4,780 850 2,000 E F G Monthly Plan Monthly Act Use the earned value table (all amounts indicated are dollars) to determine the Schedule Performance Index (SPI) given the indicated state of the project.(8/100) a. 0.88 b. 1.13 C. 0.96 d. 1.0