Question: Activity C in a project has an earliest start time (ES) of 8, an earliest finish time (EF) of 12, a latest start time (LS)
Activity C in a project has an earliest start time (ES) of 8, an earliest finish time (EF) of 12, a latest start time (LS) of 13, and a latest finish time (LF) of 17. Assume no other activities are delayed, the maximum slack time for activity C is
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts