Question: Activity C in a project has an earliest start time (ES) of 8, an earliest finish time (EF) of 12, a latest start time (LS)

Activity C in a project has an earliest start time (ES) of 8, an earliest finish time (EF) of 12, a latest start time (LS) of 13, and a latest finish time (LF) of 17. Assume no other activities are delayed, the maximum slack time for activity C is