Question: Activity Code Immediate Predecessors Optimistic A Most Likely M Pessimistic B Expected Time Variance Standard of Deviation A None 10 12 14 12 0.44 0.66
| Activity Code | Immediate Predecessors | Optimistic A | Most Likely M | Pessimistic B | Expected Time | Variance | Standard of Deviation |
| A | None | 10 | 12 | 14 | 12 | 0.44 | 0.66 |
| B | None | 4 | 8 | 10 | 7.66 | 1 | 1 |
| C | B | 6 | 6 | 6 | 6 | 0 | 0 |
| D | B | 3 | 6 | 10 | 6.16 | 1.36 | 1.16 |
| E | A,C | 1 | 2 | 3 | 2 | 0.11 | 0.33 |
| F | A,C,D | 1 | 2 | 4 | 2.16 | 0.25 | 0.5 |
| G | E | 2 | 2 | 6 | 2.66 | 0.44 | 0.66 |
| H | E | 3 | 5 | 6 | 4.83 | 0.25 | 0.5 |
| I | G,F | 4 | 5 | 6 | 5 | 0.11 | 0.33 |
The Critical Path is A-E-G-I=21.66
1- What is the risk that this project will exceed 27 weeks?