Question: Activity Code Immediate Predecessors Optimistic A Most Likely M Pessimistic B Expected Time Variance Standard of Deviation A None 10 12 14 12 0.44 0.66

Activity Code

Immediate Predecessors

Optimistic

A

Most Likely

M

Pessimistic

B

Expected Time

Variance

Standard of Deviation

A

None

10

12

14

12

0.44

0.66

B

None

4

8

10

7.66

1

1

C

B

6

6

6

6

0

0

D

B

3

6

10

6.16

1.36

1.16

E

A,C

1

2

3

2

0.11

0.33

F

A,C,D

1

2

4

2.16

0.25

0.5

G

E

2

2

6

2.66

0.44

0.66

H

E

3

5

6

4.83

0.25

0.5

I

G,F

4

5

6

5

0.11

0.33

The Critical Path is A-E-G-I=21.66

1- What is the risk that this project will exceed 27 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!