Question: Activity Crash Cost Maximum Crash Time Normal Time Normal Cost A 50 1 3 150 B 100 1 3 100 C 60 2 4 200
| Activity | Crash Cost | Maximum Crash Time | Normal Time | Normal Cost | ||
| A | 50 | 1 | 3 | 150 | ||
| B | 100 | 1 | 3 | 100 | ||
| C | 60 | 2 | 4 | 200 | ||
| D | 60 | 2 | 3 | 200 | ||
| E | 70 | 1 | 4 | 200 | ||
| F | 0 | 0 | 1 | 150 | ||
| | ||||||
| Step | Activity | Crash Time | Cost | Direct Cost | Total Time | |
| 0 | 1,000 | 12 | ||||
| 1 | ||||||
| 2 | ||||||
| 3 | ||||||
| 4 | ||||||
| 5 | ||||||
| 6 | ||||||
| 7 | ||||||
| 8 | ||||||
| 9 | ||||||
| 10 | ||||||