Question: Activity Crash Cost (Slope) Maximum Crash Time 0 A Normal Time 2 3 5 B $100 $40 $60 $20 $40 Normal Cost $100 $200 $200


Activity Crash Cost (Slope) Maximum Crash Time 0 A Normal Time 2 3 5 B $100 $40 $60 $20 $40 Normal Cost $100 $200 $200 $200 $200 $150 $150 D E F 5 1 2 3 2 2 0 5 4 2 G B D Project Duration: 14 3 5 Critical Path or Paths: A 2x E G 2x 5 5 Total Direct Cost: F 4 B D Project Duration: 13 Critical Path or Paths: A 2x G 2x C Activities Changed: F Total Direct Cost: B D Project Duration: 12 Critical Path or Paths: A 2x G Activities Changed: F Total Direct Cost: B D Project Duration: 11 Critical Path or Paths: . 2x E G 2x Activities Changed: F Total Direct Cost: B D Project Duration: 10 Critical Path or Paths: A 2x G 2x Activities Changed: Total Direct Cost: B D Project Duration: 9 Critical Path or Paths: A 2x G 2x Activities Changed: Total Direct Cost: B D Project Duration: 8 Critical Path or Paths: A 2x G 2x Activities Changed: Total Direct Cost: 14 13 12 11 10 9 8 1200 Project Duration Direct Costs Indirect Costs Total Costs 700 650 600 550 500 450 400
Critical Path or Paths: \begin{tabular}{|cccccccc|} \hline Project Duration & 14 & 13 & 12 & 11 & 10 & 9 & 8 \\ Direct Costs & 1200 & & & & & & \\ Indirect Costs & 700 & 650 & 600 & 550 & 500 & 450 & 400 \\ Total Costs & & & & & & & \\ \hline \end{tabular}Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts