Question: Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while
Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is definitely true?
Select one:
a. D is critical, and has zero slack.
b. C is completed before B.
c. D has no slack but is not critical.
d. F is critical, and has zero slack.
e. B is a critical activity.