Question: Question 7 ( 1 point ) Activity D on a CPM network has predecessors B and C , and has successor F . D has
Question point
Activity D on a CPM network has predecessors and and has successor D has duration Bs earliest finish is while Cs is Fs late start is Which of the following is definitely true?
B is a critical activity.
C is completed before B
is critical and has zero slack.
D has no slack but is not critical.
is critical and has zero slack.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
