Question: Question 7 ( 1 point ) Activity D on a CPM network has predecessors B and C , and has successor F . D has

Question 7(1 point)
Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is definitely true?
B is a critical activity.
C is completed before B.
F is critical and has zero slack.
D has no slack but is not critical.
D is critical and has zero slack.